(HBO) – Nguyen Van Quang, Deputy Secretary of the Party Committee and Chairman of the People's Committee of Hoa Binh province has requested relevant agencies to work out a plan and prioritize funding for the site clearance of road 435.
Quang made the request
while inspecting site clearance for the project on upgrading road 435 on April
19 morning. He was accompanied by Vice Chairman of the provincial People's
Committee Bui Van Khanh.

Chairman of the provincial People’s Committee Nguyen Van Quang speaks at
the working session.
Chairman of the provincial People's Committee Nguyen Van Quang and the
delegation inspect site clearance for the project on upgrading road 435.
Road 435 stretches as far as 10.2km, starting from the intersection of Cun
slope, Thai Binh ward, Hoa Binh city on the way to Binh Thanh ward, Cao Phong
district. It was built in November 2016 and is scheduled for completion in 2020
at a total cost of 283 billion VND by the management board for transport
construction projects. Up to 76.5 billion VND has been disbursed. Nearly 14.8
percent of work has been completed while the progress of site clearance is
slower than expected.
Concluding the working session, Quang said the major project plays an important
role in improving transport, socio-economic development, especially given that
Hoa Binh lake is zoned off as a national tourist area. The project began in
late 2016 but its progress is slow with difficulties regarding site clearance
and compensation, partly due to the loose coordination between the investor and
local administrations.
In order to ensure the project’s progress, Chairman of the provincial People’s
Committee asked the investor to work closely with departments and agencies
concerned and People’s Committees of cities and districts to devise detailed
plans on the progress of site clearance and the safety of households vulnerable
to construction before May 20.
The investor was required to hold monthly meetings with departments and
agencies to deal with difficulties while relevant units must work closely
together to prioritise funding for site clearance, resettlement, thus making it
easier for the contractor to complete the project as planned.
The Standing Board of the Hoa Binh provincial Party Committee met on March 18 to review and guide major investment projects aimed at boosting local socio-economic development.
The air is thick with the hum of drills and the clatter of machinery as the Hoa Binh – Moc Chau expressway takes shape amid the rugged terrain. Welding sparks illuminate the faces of workers, and concrete mixers churn relentlessly, laying fresh pavement on the newly-carved road. The construction site buzzes with a palpable sense of urgency, particularly in Hoa Binh province where the expressway's future is being forged.
The northern province of Hoa Binh, with over 467,000 hectares of natural forest and more than 100,000 hectares of production forest, holds significant potential for carbon credit market development.
Replacing substandard houses with more sturdy ones by June 30 is the direction given by Nguyen Phi Long, alternate member of the Party Central Committee and Secretary of the Hoa Binh provincial Party Committee, at a meeting held in early March by the provincial Steering Committee for the programme to eliminate temporary and dilapidated houses for the needy.
Recognising digital transformation as an inevitable trend, authorities and agencies in Hoa Binh have made great efforts in the work by focusing on three core pillars - digital government, digital society, and digital economy, resulting in enhanced competitiveness, improved investment climate, and ensured economic and social welfare.
In recent years, Da Bac district has improved administrative reform with a one-stop shop mechanism, streamlined inter-agency procedures, and a shift to digital platforms. These efforts have enhanced public service efficiency and contributed to local socio-economic development.