The provincial People’s Committee has worked to accelerate the construction of the Hoa Binh – Hanoi highway and the Hoa Binh – Moc Chau section of the Son La highway, which received in-principle approval from the provincial People’s Council in 2021.
Construction sped up for the highway section
that runs through Du sang Commune, Kim Boi district.
Kim Boi and Luong Son districts and Hoa Binh
city rushed to carry out compensation and resettlement work.
Kim Boi issued 18 decisions to retrieve 24.52
hectares of land in Du Sang, Binh Son, Vinh Tien, Dong Bac, and Vinh Dong
communes and Bo town. As much as 56.96 billion VND (2.31 million USD) was
disbursed for compensation and site clearance costs. The district also
implemented three sub-projects to develop a resettlement area in Du Sang and
Vinh Tien communes, and one in Ving Dong commune.
Meanwhile, Luong Son district approved four
decisions on land and asset compensation with a total value of 26 billion VND.
It expects to hand over around 1.5 kilometres of road in March.
As for Hoa Binh city, compensation measures for
122 households is being penned while a decision on compensation plan for
graves, land and assets on land worth 224 million VND has been approved. The
city is proposing a compensation plan for residential land and agricultural
land valued some 20 billion VND.
The management board of the local transport
projects joined hands with competent departments and sectors to remove
bottlenecks regarding land filling plans, waste disposal arrangements, changes
in forest use purposes, and moving electricity lines.
After the site clearance was completed, the
contractor carried out construction on the section connecting Kim Boi district
with Hoa Lac – Hoa Binh expressway intersection. To date, 61.08% of the
workload has been completed.
Vice Chairman of the Kim Boi district People’s
Committee Tran Tuan Son said that the construction is underway at the sites of
Chieng bridge (Vinh Dong commune), Bai Chau bridge (Dong Bac commune), Dong
Ngoai bridge (Vinh Tien commune), Kham bridge (Binh Son commune), and Chuon and
Chuon 1 bridges (Du Sang commune).
The district is working to accelerate site
clearance at the remaining three sites, he added.
The highway construction project is among the
key ones which will create a locomotive for local socio-economic development.
Therefore, the provincial People’s Committee has paid due attention to handling
roadblocks to push ahead the construction progress. Most recently, Vice
Chairman of the provincial People’s Committee Quach Tat Liem inspected the
construction progress at the sites. He asked the investors, departments,
sectors, districts and city where the highways run through to drastically
settle the site clearance work and accelerate construction for the roads.
The Standing Board of the Hoa Binh provincial Party Committee met on March 18 to review and guide major investment projects aimed at boosting local socio-economic development.
The air is thick with the hum of drills and the clatter of machinery as the Hoa Binh – Moc Chau expressway takes shape amid the rugged terrain. Welding sparks illuminate the faces of workers, and concrete mixers churn relentlessly, laying fresh pavement on the newly-carved road. The construction site buzzes with a palpable sense of urgency, particularly in Hoa Binh province where the expressway's future is being forged.
The northern province of Hoa Binh, with over 467,000 hectares of natural forest and more than 100,000 hectares of production forest, holds significant potential for carbon credit market development.
Replacing substandard houses with more sturdy ones by June 30 is the direction given by Nguyen Phi Long, alternate member of the Party Central Committee and Secretary of the Hoa Binh provincial Party Committee, at a meeting held in early March by the provincial Steering Committee for the programme to eliminate temporary and dilapidated houses for the needy.
Recognising digital transformation as an inevitable trend, authorities and agencies in Hoa Binh have made great efforts in the work by focusing on three core pillars - digital government, digital society, and digital economy, resulting in enhanced competitiveness, improved investment climate, and ensured economic and social welfare.