Given the importance of the Hoa Binh - Moc Chau Expressway (the section from Km19+000 to Km53+000 in Hoa Binh province) to socio-economic development of the province and the region, Hoa Binh is boosting coordination with the investor and relevant units to address difficulties and obstacles to speed up the settlement of procedures so as to launch construction on schedule.
Officials from management board for transportation
works construction investment projects coordinate to examine and promote site
clearance in vicinity of Da Do hamlet in Thanh Son commune, Mai Chau district.
The Hoa Binh - Moc Chau Expressway project (the
Km19+000 - Km53+000 section) is invested with almost 10 trillion VND (399
million USD) in total, comprising over 8.24 trillion VND from the central
budget and 1.75 trillion VND from the provincial one. It starts in Da Bac town
of Da Bac district in Hoa Binh province and ends in Chieng Yen commune of Van
Ho district, Son La province.
Implemented since 2022, the project is scheduled
to be completed in 2028. In the first phase, the road will have two lanes and
total width of 12 metres, including 11 metres of road surface. Once fully
completed, it will meet expressway standards and have a design speed of 80km
per hour. The route will also include three tunnels and 30 bridges.
Dinh Anh Tuan, Director of the provincial
Transport Department and deputy head of the assistant group for the project,
said the group has given advice to the chairperson of the provincial People’s
Committee about solutions and orientations for accelerating the compilation and
verification of the technical design dossier and cost estimates.
Bui Ngoc Tam, Director of the management board
for transportation works construction investment projects, noted under the
provincial administration’s direction, the board has been working closely with
relevant units to prepare necessary conditions for starting work on the project
on the occasion of the National Day (September 2) as scheduled.
He added the project was allocated more than
4.52 trillion VND, 95.2 billion VND of which has been disbursed. All the 4.65
trillion VND sourced from the socio-economic recovery and development programme
for the project is expected to be disbursed fully by December 31, 2024.
To ensure work starts as planned, the provincial
People’s Committee has proposed the Ministry of Natural Resources and
Environment, the Ministry of Construction, the Ministry of Transport, along
with related parties continue assisting Hoa Binh to tackle bottlenecks to the
project implementation, change farmland and forest land use purposes, together
with other issues to accelerate progress and promote investment
effectiveness.
With a focus on maintaining a close contact with the people, local authorities at all levels of Hoa Binh have implemented a range of measures to ensure security and order in ethnic minority-inhabited areas, improving their legal awareness, combating crime and social vices, and contributing to maintaining political stability and social order, while promoting socio-economic development in these areas.
On November 8th, Ngai hamlet, Thach Yen commune (Cao Phong) organized the Great National Solidarity Festival in 2024. There was the attendance of Mr. Bui Van Khanh, the Deputy Secretary of the Provincial Party Committee, the Chairman Provincial People's Committee; Colonel Trinh Duc Thiem, the Commander of the Provincial Military Command...
Hoa Binh Power Company (PC Hoa Binh) has proactively rolled out plans and solutions to ensure the stable and safe operation of the electricity grid, so as to meet the increasing needs of customers in the year-end period.
To achieve the goal of becoming a new-style rural district by 2025, the authorities of Yen Thuy district are working diligently to meet various criteria, with a particular focus on developing model new-style rural residential areas and model gardens.
Luong Son district is leveraging its existing advantages and maximizing resources to improve infrastructure, aiming to achieve town status by 2025.
Hoa Binh province has employed diverse measures to remove temporary and dilapidated houses for low-income families over the past time. The effort has received the support from the State, all-level agencies, as well as individuals in and outside the province, helping poor and disadvantaged households, especially ethnic minority people, repair or build new homes.