The steering committee for key projects of Hoa Binh province convened on May 14 to assess the progress of major ongoing developments


Nguyen Phi Long, alternate member of the Party Central Committee and Secretary of the provincial Party Committee, speaks at the meeting.


The Department of Finance delivers a report on the progress of key projects in the province. 

Currently, Hoa Binh has 14 key projects under the committee’s direction, comprising one public-private partnership (PPP) project, five transport and irrigation projects funded by public investment, and eight non-budgetary projects. Recently, the standing board of the Party Committee of the provincial People’s Committee added 10 more non-budgetary projects to the priority list, raising the total number to 24, with a combined investment exceeding 102 trillion VND (3.9 billion USD). Among these, 11 projects have commenced, with progress on schedule. 

During the meeting, delegates noted that disbursement for key public-funded projects remains low due to bottlenecks in site clearance, which has hindered construction progress. Key challenges include discrepancies in land mapping and documentation, and difficulties in verifying land origins. Furthermore, recent changes in compensation prices for crops and vegetation along the Hoa Binh – Moc Chau expressway have led to public disagreement over compensation rates. Compulsory land clearance enforcement also faces hurdles due to coordination issues. 

Representatives from districts and city called on the provincial People’s Committee to provide unified guidance on compensation pricing to accelerate land clearance. They urged stronger coordination among relevant departments and local authorities to finalise land origin verification and registration procedures to facilitate compensation and resettlement efforts. Localities expressed commitment to completing land clearance for the projects by June to hand over cleared sites to investors. 

In his closing remarks, Secretary of the provincial Party Committee Nguyen Phi Long highlighted that 11 key projects have broken ground over the 2023–2024 period. He emphasised the shift from passivity to proactive coordination across departments and agencies, driven by clearly assigned responsibilities and deadlines. However, he acknowledged that land clearance remains the most pressing issue, due to legal and policy constraints, challenges in public communication, and limitations in the capacity of relevant officials. 

He instructed the standing board of the Party Committee of the People’s Committee to continue directing efforts to complete compensation and land clearance for key transport projects already underway, with the goal of handing over cleared land by June to expedite construction. The pPeople’s Committee was also tasked with completing procedures to begin work on the Hoa Binh – Hoa Lac road expansion, tourism infrastructure, and educational facilities across the province. Regarding the 10 newly added key projects, he urged the People’s Committee to work closely with investors to review, guide, and support completion of necessary procedures, aiming to start construction as early as August.


Related Topics


Hoa Binh maintains stable economic growth in four months

The economic landscape of Hoa Binh province continued its impressive upward trajectory through the first four months of 2025, according to a recent report from the provincial Department of Finance. The local authority has directed departments and sectors to keep close tabs on growth scenarios for each quarters and remove bottlenecks, striving to complete the set growth targets.

Hoa Binh prioritises infrastructure investment to propel industrial, handicraft sectors 

As part of efforts to restructure and accelerate the development of its industrial and handicraft sectors, Hoa Binh province is focusing on the development of industrial parks (IPs) and industrial clusters (ICs) with synchronous infrastructure to attract strong investment.

Opportunities to expand development space

In recent times, Hoa Binh province has shown its determination and high sense of responsibility in seriously implementing the directives of the Party Central Committee and its Politburo and Secretariat regarding the streamlining of the political system’s organisational apparatus and the development of a two-level local administration system. The aim is to build a commune-level administration that is close to the people, attentive to their needs, and capable of quickly responding to the demands of both businesses and citizens, while also opening up new development spaces.

Hoa Binh carves out a distinct spot on Vietnam’s new service map

Over the past three years, the northern mountainous province of Hoa Binh has begun redefining its position on Vietnam’s service landscape with a series of distintive commercial models, from highland night markets, pedestrian-friendly streets, to logistics centres tied to local agricultural products.

Hoa Binh advances sustainable forestry with FSC certification

Hoa Binh city has marked a significant step in sustainable forest management as nearly 1,450 hectares of its plantation forests have been granted Forest Stewardship Council (FSC) certification, an international standard required to access major wood markets such as the EU, the US, and Japan.

Work begins on Xuan Thien Hoa Binh lime and light powder factory

Construction on the Xuan Thien Hoa Binh lime and light powder factory in Yen Bong commune, Lac Thuy district - a key project of Hoa Binh province - started on April 24.