(HBĐT) – The construction of Hoa Binh Bridge 3 is a key project of Hoa Binh City. The project started in 2016 with a total investment of nearly 435 billion VND. Up till now, the project of Hoa Binh Bridge 3 has achieved the volume of over 260 billion VND. The contractor is urgently implementing items to ensure that the completion of the project will be in use in 2019.


Taking advantage of the favorable weather, the joint venture contractor have accelerated the construction progress of Hoa Binh Bridge 3 across Da river, trying to inaugurate in 2019.

The project of  Hoa Binh Bridge 3 belongs to phase 2 of "The Program for the Northern Mountainous Urban - Hoa Binh City". The investor is the People's Committee of Hoa Binh City, a partnership with Trung Chinh Trading and Construction Co., Ltd. and Hoang Son company is the construction contractor.

Hoa Binh Bridge 3 is designed to be constructed of permanent pre-stressed reinforced concrete. The bridge has a length of over 535 meters with a path of nearly 210 meters. The width of the bridge is 16 meters, in which the lane is 12 meters in width. The total width of the bridge is more 4 meters than that of Hoa Binh Bridge 1.

During the past time, Trung Chinh Trading and Construction Co., Ltd - the bridge construction unit has mobilized machinery, human resources and materials to construct the bridge abutments and has organized construction to make 3 shifts to accelerate the construction progress.

Up till now, the project for Hoa Binh Bridge 3 has achieved the volume of over 260 billion VND. The payment value including the advance and payment records has reached 231 billion VND. The main items are being concentrated to complete, the boundary on the left bank has been completed.

At the same time, the clearance work is being completed in rush, creating the conditions for Hoang Son Company to construct the path as soon as possible.

It is expected that in April, 2019 the construction units will officially implement the boundaries of Hoa Binh Bridge 3, ensuring to complete and put it into use in 2019, helping to reduce the overloading of Hoa Binh Bridge 1 in the past time.

 

Related Topics


Several communes in Lac Thuy district struggle to promote OCOP products

In Lac Thuy district, communes have been succeeded in promoting their One Commune-One Product (OCOP) products while others are still struggling to position their typical farming products in market. Some communes in the district still fail to have their products met OCOP programme’s requirements, while others have seen their certifications expired.

Measures sought to improve PCI’s informal component indexes

The inspectorate agency of Hoa Binh province has issued Official Dispatch No. 1090/TTr-PCTN to provincial departments, agencies, localities, business associations, enterprises, and investors regarding measures to improve informal component indexes of the Provincial Competitiveness Index (PCI).

Hoa Binh works to enhance investment climate: Responsibility, action enable Kim Boi to welcome billion-dollar projects

Hoa Binh is taking concrete steps to improve its investment environment, with a strong focus on supporting businesses, settling obstacles for strategic investors, and creating opportunities for robust development in the coming years.

Nhuan Trach industrial park accelerates construction to welcome investors

Under the blazing early summer sun, the construction site of Nhuan Trach Industrial Park (IP) in Luong Son district is abuzz with activities from dawn to dusk, a testament to the determination of the investor to meet their construction targets on schedule.